North East Community Restoration and Development Project – NECORD II – (ADB)

 

Cost : Rs. 5500 Mn.                                                        2005 to 2009

 

Under the sectors Education, Health, Agriculture, Road, Shelter, Institutional Development, Irrigation, Social Welfare, Livestock, Upfront activities, Community Development, Water Supply & Sanitation, and Fisheries, 163 projects out of the 226 projects were approved by ADB. Tenders have been called for 153 projects and tenders were awarded to 148 projects. 70 Sub Projects have been completed in the Eastern Province.

 

Cumulative expenditure as at 31st October 2007 was Rs: 1,835.756 Mn. (For Northern and Eastern Provinces)

 