Progress on NEHRP as at 28th February 2008
Phase  III
    Trincomalee Batticalaoa Amparai Total Expenditure
  Unit Target Achieved Target Achieved Target Achieved Rs:Mn
                 
Construction of Foundation Number 12 10 80 6 200 159 52.61
                 
Construction of Super Structure Number 305 42 1,056 101 1,083 406 48.50
                 
Construction of Roof Number 862 45 2,856 146 2,386 747 66.34
                 
Completion of Houses Number 965 4 2,469 9 2,391 0 0.65
                 
Masonry Training Persons 30 Done 25 On Going 0 0 n.a
                 
Carpentry Training Persons 30 Done 25 On Going 30 On Going n.a