| Progress on NEHRP as at 28th February 2008 | |||||||||
| Phase III | |||||||||
| Trincomalee | Batticalaoa | Amparai | Total Expenditure | ||||||
| Unit | Target | Achieved | Target | Achieved | Target | Achieved | Rs:Mn | ||
| Construction of Foundation | Number | 12 | 10 | 80 | 6 | 200 | 159 | 52.61 | |
| Construction of Super Structure | Number | 305 | 42 | 1,056 | 101 | 1,083 | 406 | 48.50 | |
| Construction of Roof | Number | 862 | 45 | 2,856 | 146 | 2,386 | 747 | 66.34 | |
| Completion of Houses | Number | 965 | 4 | 2,469 | 9 | 2,391 | 0 | 0.65 | |
| Masonry Training | Persons | 30 | Done | 25 | On Going | 0 | 0 | n.a | |
| Carpentry Training | Persons | 30 | Done | 25 | On Going | 30 | On Going | n.a | |